Difference between SPPL, UKL-UPL and AMDAL documents for PLTS Environmental Permits

April 30, 2023

Planning for the development of Solar Power Plants (PLTS) based on environmental management should be in accordance with Government Regulation (PP) and regulations mandated by the Ministry of Environment and Forestry (KLHK). According to Government Regulation Number 22 of 2021 concerning the Implementation of Environmental Protection and Management, environmental documents consist of three types: Statements of Environmental Management and Monitoring Capability (SPPL), Environmental Management Efforts and Environmental Monitoring Efforts (UKL-UPL), and Environmental Impact Analysis (AMDAL).[1]

The required environmental permit documents depend on the type of business plan and/or activity being carried out. The table below outlines the criteria for each type of environmental permit document in the planning of PLTS development.

Table 1. Differences in Criteria for PLTS Environmental Permit Documents.[2]

Points of Difference

SPPL

UKL-UPL

AMDAL

Preparation Time Prior to business/activity implementation Prior to business/activity implementation Prior to business/activity implementation

Scale of PLTS Development Activity

  • Kapasitas PLTS < 1 MWp
  • Kegiatan dengan potensi dampak alih fungsi lahan dan dampak lingkungan lainnya tidak ada atau kecil
  • Kapasitas PLTS 1 s.d. < 50 MWp
  • Kegiatan dalam satu lokasi dengan potensi dampak alih fungsi guna lahan dan dampak lingkungan lainnya tidak besar
  • Kapasitas PLTS ≥ 50 MWp
  • Kegiatan dalam satu lokasi dengan potensi dampak alih fungsi guna lahan dan dampak lingkungan lainnya sangat besar

Penyusun

Pemrakarsa kegiatan

Konsultan/Pemrakarsa kegiatan

Konsultan tersertifikasi (kompetensi penyusun AMDAL)*

Mekanisme penyusunan

Mengisi formulir SPPL dan melakukan pendaftaran langsung ke instansi/lembaga lingkungan hidup daerah setempat

Melalui tahap pemeriksaan dokumen UKL/UPL sebelum mendapatkan rekomendasi persetujuan atau penolakan UKL/UPL

Melalui tahapan penilaian oleh Komisi Penilai AMDAL sebelum mendapatkan Surat Keputusan Kelayakan/Izin Lingkungan

Media pengajuan

  • Pemerintah pusat/daerah melalui lembaga lingkungan setempat
  • Pengembang (pelaku usaha) melalui OSS**
  • Pemerintah pusat/daerah melalui lembaga lingkungan setempat
  • Pengembang (pelaku usaha) melalui OSS
  • Pemerintah pusat/daerah melalui lembaga lingkungan setempat
  • Pengembang (pelaku usaha) melalui OSS

* The certificate can be coordinated with BNSP/LSP, in accordance with the criteria in the Minister of Manpower Regulation No. 122/2016

** OSS = Online Single Submission

Currently, environmental permit guidelines refer to Minister of Environment Regulation (Permen LH) No. 16 of 2012 (for the Central/Regional Government) and Minister of Environment and Forestry Regulation (Permen LHK) No. P.26 of 2018 (for private developers/business operators). The preparation of environmental permit documents is adjusted to the capacity of PLTS, whether to prepare SPPL, UKL-UPL, or AMDAL, as indicated in the table above.[2]

As the Proyek ACCESS UNDP is building PLTS with a capacity of less than 1 MWp, an SPPL document is required before the construction of PLTS is carried out as a statement of the commitment of the activity initiator to manage and monitor the environmental impact of the activity.

Author: Dawam Faizul Amal

References:

  1. Pemerintah Pusat, Peraturan Pemerintah (PP) Nomor 22 Tahun 2021 tentang Penyelenggaraan Perlindungan dan Pengelolaan Lingkungan Hidup. Indonesia: LN.2021/No.32, TLN No.6634, jdih.setkab.go.id?: 374 hlm., 2021, p. 15.
  2. Kementerian Energi dan Sumber Daya Mineral (KESDM), Panduan Pengelolaan Lingkungan Pembangkit Listrik Tenaga Surya (PLTS). Jakarta: Kementerian Energi dan Sumber Daya Mineral (KESDM), 2020.